Question 416 - CAPM discussion
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
A.
Perform Qualitative Risk Analysis
B.
Perform Quantitative Risk Analysis
C.
Plan Risk Management
D.
Plan Risk Responses