Which of the following project documents is an input to the Control Scope process?

A.
Vendor risk assessment diagram
Answers
A.
Vendor risk assessment diagram
B.
Risk register
Answers
B.
Risk register
C.
Requirements traceability matrix
Answers
C.
Requirements traceability matrix
D.
Area of responsibility summary
Answers
D.
Area of responsibility summary
Suggested answer: C