The progressive detailing of the project management plan is called:

A.
expert judgment.
Answers
A.
expert judgment.
B.
rolling wave planning.
Answers
B.
rolling wave planning.
C.
work performance information.
Answers
C.
work performance information.
D.
specification.
Answers
D.
specification.
Suggested answer: B