List of questions
Related questions
Question 536 - CAPM discussion
What is the responsibility of the project manager and the functional manager respectively?
A.
Oversight for an administrative area; a facet of the core business
B.
Achieving the project objectives; providing management oversight for an administrative area
C.
A facet of the core business; achieving the project objectives
D.
Both are responsible for achieving the project objectives.