Question 547 - CAPM discussion

Report
Export

Which cost estimate technique includes contingencies to account for cost uncertainty?

A.
Vendor bid analysis
Answers
A.
Vendor bid analysis
B.
Three-point estimates
Answers
B.
Three-point estimates
C.
Parametric estimating
Answers
C.
Parametric estimating
D.
Reserve analysis
Answers
D.
Reserve analysis
Suggested answer: D