Which of the following is an output of the Perform Integrated Change Control process?

A.
Project document updates
Answers
A.
Project document updates
B.
Organizational process assets updates
Answers
B.
Organizational process assets updates
C.
Change requests
Answers
C.
Change requests
D.
Deliverables
Answers
D.
Deliverables
Suggested answer: A