Which of the following is an input to Control Scope?

A.
Project schedule
Answers
A.
Project schedule
B.
Organizational process assets updates
Answers
B.
Organizational process assets updates
C.
Project document updates
Answers
C.
Project document updates
D.
Work performance information
Answers
D.
Work performance information
Suggested answer: D