Lessons learned documentation is gathered during which of the following Project Management Process Groups?

A.
Planning
Answers
A.
Planning
B.
Executing
Answers
B.
Executing
C.
Closing
Answers
C.
Closing
D.
Initiating
Answers
D.
Initiating
Suggested answer: C