Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

A.
Project sponsor
Answers
A.
Project sponsor
B.
Project manager
Answers
B.
Project manager
C.
Person responsible for project scheduling
Answers
C.
Person responsible for project scheduling
D.
Person who is most familiar with the task
Answers
D.
Person who is most familiar with the task
Suggested answer: D