Question 554 - CAPM discussion

Report
Export

Which of the following is the primary output of the Identify Risks process?

A.
Risk management plan
Answers
A.
Risk management plan
B.
Risk register
Answers
B.
Risk register
C.
Change requests
Answers
C.
Change requests
D.
Risk response plan
Answers
D.
Risk response plan
Suggested answer: B