Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

A.
Cyclic
Answers
A.
Cyclic
B.
Progressive
Answers
B.
Progressive
C.
Repetitive
Answers
C.
Repetitive
D.
Iterative
Answers
D.
Iterative
Suggested answer: B