In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

A.
Start-to-start (SS)
Answers
A.
Start-to-start (SS)
B.
Start-to-finish (SF)
Answers
B.
Start-to-finish (SF)
C.
Rnish-to-finish (FF)
Answers
C.
Rnish-to-finish (FF)
D.
Finish-to-start (FS)
Answers
D.
Finish-to-start (FS)
Suggested answer: D