Question 573 - CAPM discussion

Report
Export

A required input for Create WBS is a project:

A.
quality plan.
Answers
A.
quality plan.
B.
schedule network.
Answers
B.
schedule network.
C.
management document update.
Answers
C.
management document update.
D.
scope statement.
Answers
D.
scope statement.
Suggested answer: D