Which of the following correctly explains the term "progressive elaboration'?

A.
Changing project specifications continuously
Answers
A.
Changing project specifications continuously
B.
Elaborate tracking of the project progress
Answers
B.
Elaborate tracking of the project progress
C.
Elaborate tracking of the project specifications with a change control system
Answers
C.
Elaborate tracking of the project specifications with a change control system
D.
Project specifications becoming more explicit and detailed as the project progresses
Answers
D.
Project specifications becoming more explicit and detailed as the project progresses
Suggested answer: D