Question 584 - CAPM discussion
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
A.
There is a cost underrun.
B.
There is a cost overrun.
C.
The project may not meet the deadline.
D.
The project is 20 days behind schedule.