A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

A.
There is a cost underrun.
Answers
A.
There is a cost underrun.
B.
There is a cost overrun.
Answers
B.
There is a cost overrun.
C.
The project may not meet the deadline.
Answers
C.
The project may not meet the deadline.
D.
The project is 20 days behind schedule.
Answers
D.
The project is 20 days behind schedule.
Suggested answer: B