Question 593 - CAPM discussion

Report
Export

The process of identifying the stakeholders' information needs is completed during:

A.
Plan Communications.
Answers
A.
Plan Communications.
B.
Manage Stakeholder Expectations.
Answers
B.
Manage Stakeholder Expectations.
C.
Stakeholder Analysis.
Answers
C.
Stakeholder Analysis.
D.
Identify Stakeholders.
Answers
D.
Identify Stakeholders.
Suggested answer: A