What is the most accurate rough order of magnitude (ROM)?

A.
In the Initiation phase, the estimate is in the range of +/- 50%.
Answers
A.
In the Initiation phase, the estimate is in the range of +/- 50%.
B.
In the Planning phase, the estimate is in the range of +/- 50%.
Answers
B.
In the Planning phase, the estimate is in the range of +/- 50%.
C.
In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.
Answers
C.
In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.
D.
In the Closing phase, the estimate is in the range of +/- 15%.
Answers
D.
In the Closing phase, the estimate is in the range of +/- 15%.
Suggested answer: A