Project contracts generally fall into which of the following three broad categories?

A.
Fixed-price, cost reimbursable, time and materials
Answers
A.
Fixed-price, cost reimbursable, time and materials
B.
Make-or-buy, margin analysis, fixed-price
Answers
B.
Make-or-buy, margin analysis, fixed-price
C.
Time and materials, fixed-price, margin analysis
Answers
C.
Time and materials, fixed-price, margin analysis
D.
Make-or-buy, lump-sum, cost-plus-incentive
Answers
D.
Make-or-buy, lump-sum, cost-plus-incentive
Suggested answer: A