Which of the following events would result in a baseline update?

A.
A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
Answers
A.
A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
B.
A customer has approved a change request broadening the project scope and increasing the budget.
Answers
B.
A customer has approved a change request broadening the project scope and increasing the budget.
C.
One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
Answers
C.
One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
D.
One of the key project team resources has left the team and no replacement is available.
Answers
D.
One of the key project team resources has left the team and no replacement is available.
Suggested answer: B