Question 597 - CAPM discussion

Report
Export

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.
Applying calendars
Answers
A.
Applying calendars
B.
Resource leveling
Answers
B.
Resource leveling
C.
Resource planning
Answers
C.
Resource planning
D.
Resource conflict management
Answers
D.
Resource conflict management
Suggested answer: B