Which of the following is a project constraint?

A.
Twenty-five percent staff turnover is expected.
Answers
A.
Twenty-five percent staff turnover is expected.
B.
The technology to be used is cutting-edge.
Answers
B.
The technology to be used is cutting-edge.
C.
Project leadership may change due to volatile political environment.
Answers
C.
Project leadership may change due to volatile political environment.
D.
The product is needed in 250 days.
Answers
D.
The product is needed in 250 days.
Suggested answer: D