An input to the Estimate Activity Resources process is:

A.
Activity resource requirements.
Answers
A.
Activity resource requirements.
B.
Published estimating data.
Answers
B.
Published estimating data.
C.
Resource calendars.
Answers
C.
Resource calendars.
D.
Resource breakdown structure (RBS).
Answers
D.
Resource breakdown structure (RBS).
Suggested answer: C