How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

A.
Keep satisfied
Answers
A.
Keep satisfied
B.
Keep informed
Answers
B.
Keep informed
C.
Manage closely
Answers
C.
Manage closely
D.
Monitor
Answers
D.
Monitor
Suggested answer: A