The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

A.
$800
Answers
A.
$800
B.
$1000
Answers
B.
$1000
C.
$1250
Answers
C.
$1250
D.
$1800
Answers
D.
$1800
Suggested answer: A