Question 674 - CAPM discussion
The correct equation for schedule variance (SV) is earned value:
A.
minus planned value [EV - PV].
B.
minus actual cost [EV - AC].
C.
divided by planned value [EV/PV],
D.
divided by actual cost [EV/AC].