After Define Activities and Sequence Activities, the next process is:

A.
Estimate Activity Resources.
Answers
A.
Estimate Activity Resources.
B.
Estimate Activity Durations,
Answers
B.
Estimate Activity Durations,
C.
Develop Schedule.
Answers
C.
Develop Schedule.
D.
Control Schedule.
Answers
D.
Control Schedule.
Suggested answer: A