The three processes of Project Cost Management are:
A.
Estimate Costs, Control Schedule, and Control Costs.
B.
Estimate Costs, Determine Budget, and Estimate Activity Resources.
C.
Determine Budget, Control Schedule, and Estimate Activity Resources.
D.
Estimate Costs, Determine Budget, and Control Costs.