Which of the following is an output of the Conduct Procurements process?

A.
Project statement of work
Answers
A.
Project statement of work
B.
Selected sellers
Answers
B.
Selected sellers
C.
Risk register updates
Answers
C.
Risk register updates
D.
Teaming agreements
Answers
D.
Teaming agreements
Suggested answer: B