The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

A.
a control chart.
Answers
A.
a control chart.
B.
baseline.
Answers
B.
baseline.
C.
Create WBS.
Answers
C.
Create WBS.
D.
decomposition.
Answers
D.
decomposition.
Suggested answer: D