Which is a list of organizational systems that may have an impact on a project?

A.
Internal policies, company procedures, and organizational resources
Answers
A.
Internal policies, company procedures, and organizational resources
B.
Company culture, purchasing system, and project management information system
Answers
B.
Company culture, purchasing system, and project management information system
C.
Organizational structure, governance framework, and management elements
Answers
C.
Organizational structure, governance framework, and management elements
D.
Organizational process assets, enterprise environmental factors, and corporate knowledge
Answers
D.
Organizational process assets, enterprise environmental factors, and corporate knowledge
Suggested answer: D