In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

A.
Collect Requirements
Answers
A.
Collect Requirements
B.
Create work breakdown structure (WBS)
Answers
B.
Create work breakdown structure (WBS)
C.
Plan Scope Management
Answers
C.
Plan Scope Management
D.
Scope Baseline
Answers
D.
Scope Baseline
Suggested answer: A