List of questions
Related questions
Question 718 - CAPM discussion
In an agile and adaptive project, which scope management entity invokes stakeholder engagement?
A.
Collect Requirements
B.
Create work breakdown structure (WBS)
C.
Plan Scope Management
D.
Scope Baseline
Your answer:
0 comments
Sorted by
Leave a comment first