Question 734 - CAPM discussion

Report
Export

During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?

A.
Activity dependencies
Answers
A.
Activity dependencies
B.
Work package risks
Answers
B.
Work package risks
C.
Description of work
Answers
C.
Description of work
D.
Resource estimates
Answers
D.
Resource estimates
Suggested answer: C