Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

A.
Eleven weeks
Answers
A.
Eleven weeks
B.
Nine weeks
Answers
B.
Nine weeks
C.
Eight weeks
Answers
C.
Eight weeks
D.
Ten weeks
Answers
D.
Ten weeks
Suggested answer: D