List of questions
Related questions
Question 735 - CAPM discussion
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
A.
Eleven weeks
B.
Nine weeks
C.
Eight weeks
D.
Ten weeks
Your answer:
0 comments
Sorted by
Leave a comment first