A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

A.
create the project management plan.
Answers
A.
create the project management plan.
B.
identify the project objectives.
Answers
B.
identify the project objectives.
C.
review and update stakeholder engagement.
Answers
C.
review and update stakeholder engagement.
D.
create the schedule baseline.
Answers
D.
create the schedule baseline.
Suggested answer: C