Under which circumstances should multiple projects be grouped in a program?

A.
When they are needed to accomplish a set of goals and objectives for an organization
Answers
A.
When they are needed to accomplish a set of goals and objectives for an organization
B.
When they have the same project manager and the same organizational unit
Answers
B.
When they have the same project manager and the same organizational unit
C.
When they have the same scope, budget, and schedule
Answers
C.
When they have the same scope, budget, and schedule
D.
When they are from the same unit of the organization
Answers
D.
When they are from the same unit of the organization
Suggested answer: A