Question 740 - CAPM discussion

Report
Export

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?

A.
Project activities
Answers
A.
Project activities
B.
Work packages
Answers
B.
Work packages
C.
Planning packages
Answers
C.
Planning packages
D.
Project deliverables
Answers
D.
Project deliverables
Suggested answer: B