ExamGecko
Home Home / PMI / CAPM
Question list
Search
Search

Question 754 - CAPM discussion

Report
Export

A sponsor asks a project manager to provide a project's expected total costs based on its progress.

What formula should the project manager use to determine this?

A.
Eamed value (EV) / actual cost (AC)
Answers
A.
Eamed value (EV) / actual cost (AC)
B.
Estimate at completion (EAC) - AC
Answers
B.
Estimate at completion (EAC) - AC
C.
Budget at completion (BAC) / cost performance index (CPI)
Answers
C.
Budget at completion (BAC) / cost performance index (CPI)
D.
EV - planned value (PV)
Answers
D.
EV - planned value (PV)
Suggested answer: B
asked 23/09/2024
irwandi irwandi
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first