Which of the following can a project manager use to represent dellned team member roles in a group of tasks?

A.
Work breakdown structure (WBS)
Answers
A.
Work breakdown structure (WBS)
B.
Responsibility assignment matrix (RAM)
Answers
B.
Responsibility assignment matrix (RAM)
C.
Organizational breakdown structure (OBS)
Answers
C.
Organizational breakdown structure (OBS)
D.
Resource breakdown structure (RBS)
Answers
D.
Resource breakdown structure (RBS)
Suggested answer: B