Which of the following can a project manager use to represent dellned team member roles in a group of tasks?
A.
Work breakdown structure (WBS)
B.
Responsibility assignment matrix (RAM)
C.
Organizational breakdown structure (OBS)
D.
Resource breakdown structure (RBS)