A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?

A.
Three-point estimating
Answers
A.
Three-point estimating
B.
Parametric estimating
Answers
B.
Parametric estimating
C.
Bottom-up estimating
Answers
C.
Bottom-up estimating
D.
Data analysis
Answers
D.
Data analysis
Suggested answer: C