Question 773 - CAPM discussion
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is the project manager using?
A.
Three-point estimating
B.
Parametric estimating
C.
Bottom-up estimating
D.
Data analysis