Which statement about identification and engagement of stakeholders during a project is correct?

A.
Project stakeholders should be Identified and engaged in every phase of the project to influence the success of the project directly.
Answers
A.
Project stakeholders should be Identified and engaged in every phase of the project to influence the success of the project directly.
B.
Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.
Answers
B.
Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.
C.
Project stakeholders should be identified when the project chatter is being completed and engaged during requirements gathering.
Answers
C.
Project stakeholders should be identified when the project chatter is being completed and engaged during requirements gathering.
D.
Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process.
Answers
D.
Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process.
Suggested answer: A