Which of the following are outputs from the process of creating a work breakdown structure (WBS)?

A.
Project scope statement and accepted deliverables
Answers
A.
Project scope statement and accepted deliverables
B.
Scope baseline and project documents update
Answers
B.
Scope baseline and project documents update
C.
Accepted deliverables and enterprise environmental factors
Answers
C.
Accepted deliverables and enterprise environmental factors
D.
Scope baseline and work performance information
Answers
D.
Scope baseline and work performance information
Suggested answer: B