A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?

A.
The project manager should identify and deal with stakeholders only during the execution phase.
Answers
A.
The project manager should identify and deal with stakeholders only during the execution phase.
B.
Stakeholder satisfaction should be identified immediately and managed as a project objective.
Answers
B.
Stakeholder satisfaction should be identified immediately and managed as a project objective.
C.
The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
Answers
C.
The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
D.
Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Answers
D.
Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Suggested answer: B