Question 780 - CAPM discussion
A company must implement sales software because it is opening a new branch in a foreign market.
Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.
Which type of life cycle would the project manager use in this case?
A.
Predictive life cycle
B.
Waterfall life cycle
C.
Hybrid life cycle
D.
Product life cycle