Which tool should a project manager consider to deal with multiple sources of risk?

A.
An updated risk register
Answers
A.
An updated risk register
B.
Risk breakdown structure
Answers
B.
Risk breakdown structure
C.
Issue log
Answers
C.
Issue log
D.
Stakeholder register
Answers
D.
Stakeholder register
Suggested answer: B