Question 783 - CAPM discussion
When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?
A.
Iterative scheduling with backlog
B.
On-demand scheduling
C.
Life cycle scheduling with backlog
D.
Defining Iterative activities