Which action should the project manager take after the team finishes executing the scope?
A.
Verify the deliverables to ensure that they are correct and meet the customer's satisfaction.
B.
Accept all the deliverables and deliver them to the customer for final acceptance.
C.
Conduct a joint session with the customer, change the deliverables, and then request approval.
D.
Check that all change requests were implemented and release deliverables to the customer.