When should Project Risk Management be conducted?

A.
Project Planning
Answers
A.
Project Planning
B.
Monitoring and Controlling
Answers
B.
Monitoring and Controlling
C.
Quality Planning
Answers
C.
Quality Planning
D.
Throughout the project lifecycle
Answers
D.
Throughout the project lifecycle
Suggested answer: C