What is the first step in the Stakeholder Management process?

A.
Plan Stakeholder Engagement
Answers
A.
Plan Stakeholder Engagement
B.
Identify Stakeholders
Answers
B.
Identify Stakeholders
C.
Manage Stakeholder Responsibility
Answers
C.
Manage Stakeholder Responsibility
D.
Monitor Stakeholder Activity
Answers
D.
Monitor Stakeholder Activity
Suggested answer: B