What is the project manager's responsibility in Project Integration Management?
A.
Ensuring that requirements-related work is clarified in the project management plan
B.
Investing sufficient effort in acquiring, managing, motivating, and empowering the project team
C.
Combining the results in all other knowledge areas, and overseeing the project as a whole
D.
Developing a strategy to ensure effective stakeholder communication