Question 791 - CAPM discussion
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?
A.
Plan Resource Management
B.
Estimate Activity Resources
C.
Estimate Costs
D.
Acquire Resources
Your answer: